District of Chetwynd - Main Sanitary Lift Station Upgrades


Chetwynd, British Columbia

 

Client

District of Chetwynd

Architect

Onsite Engineering Ltd.

Engineer

Watanabe Engineering Ltd.

General

Northern Legacy Construction Ltd.

Project Type

Renovation

Location

Chetwynd BC

Construction Sector

Industrial WWTP

Status

Completed Project - October 1, 2025

Project includes new a bypass lift station and upgrades to the existing lift station: Installation of new 2-60HP 600V and 2-34HP 600V pumps, Make-Up Air unit to reduce to Zone 2 classification, 200KW 600V 3PH Generator, MCC/VFD line up, PLC and instrumentation controls, Zone 2 hazardous LED lighting upgrade, Full integration and upgrades to Grinder Controls to the PLC.